Prepping for Version Cutover

In advance of Cutover Date:

Back-Ups

Make sure schedules are set up (Rich’s template includes standard schedules but any server side database schedules will need to be manually set up in advance using a back-up copy of the file in question.)
Moving Weekly, Quarterly, Yearly, and Saved Back-ups, Removed and .Dot Folders -

Move backups other than hourlies in advance of moving production [with pre-mounting drives for backups using the new name in play at that time
Sample temp. server name - (get from Rich)

Mounting Drives

You can do the mounting from either side but best done from old machine so that you don’t have to unmount after fact
Open >> File Explorer>>This PC (left side menu) >>Upper This computer Tab is visible and Map Network drive button is available on toolbar
\\prd-r1\c$   pre-cutover work - for moving back ups

\\dcad-fmp-prod-1\c$ for moving production files

Scheduling:

propose time with Rich

Confirm with power users

Confirm time with Rich
Plan for a couple of hours downtime for Prod 1
At Cutover Time - connect with Rich via Slack

(but also track the scheduled work in an RT Thread)
Renaming Hosts - Rich

@ cutover time requires Rich manage 2 pieces of re-naming work first so coordination must be done closely with him:  host name and DNS switch so that the new machine has the new name

This work could also take about an hour
Checking on Consoles and Remoting to both machines with their new names

Before signing off with Rich, make sure to check that you can Remote onto both servers and see consoles; open Files with FM Pro
Stopping Schedules and Closing Files - In Console -  Me

Stopping all back-up schedules on old machine

Stop files

Move data
Mounting Drive

You can do the mounting from either side but best done from old machine so that you don’t have to unmount after fact
Open >> File Explorer>>This PC (left side menu) >>Upper This computer Tab is visible and Map Network drive button is available on toolbar
\\dcad-fmp-test-1\c$
This will be slow  (2 hours for production files)

Note - if you leave your computer, your computer may go to sleep and this can impact the process
Once production files are moved, you are good to go (you can send a message at that point to users that it is back up and to report any potential issues.)

No need to worry about dailies or hourly back ups.  Those will be available on old server for enough time that

Who needs to get cutover:

RD - This just has one file.  First ask Becky about doing this.
DUE - this has a lot of files on this.  Start this before Stu leaves.  Clients will need to be at least on FM14 ( no pro 13s)   Kiosks would have to get relaunched.  
UAAP - this has some unique things. ALways check to see what ODBC drivers are on a server
Servers that should be managed better:

VPF - this is a locally managed server and it is 12 with MDS connections.  We don’t have OS nor Console access and we don’t know what else they are hosting.  Confusing who to deal with.  VPF has their own BA type folks.   

Additional Server Management Resources (Internal IS&T Resources)

Server Patching

Server Troubleshooting 

Server Migration

FileMaker Pro and FileMaker Server Documentation (Public-facing MIT Documents )

MIT Knowledge Base

IS&T Contributions

Documentation and information provided by IS&T staff members


Last Modified:

February 05, 2018

Get Help

Request help
from the Help Desk
Report a security incident
to the Security Team
Labels:
None
Enter labels to add to this page:
Please wait 
Looking for a label? Just start typing.
Feedback
This product/service is:
Easy to use
Average
Difficult to use

This article is:
Helpful
Inaccurate
Obsolete
Adaptavist Theme Builder (4.2.3) Powered by Atlassian Confluence 3.5.13, the Enterprise Wiki